ADU Permits in San Diego: City vs. County Guide

Most ADU permit delays in San Diego start with the plan set, not the agency: nobody confirmed which agency has jurisdiction, whether the lot is in the Coastal Overlay Zone, or whether the plans have everything the reviewer needs on the first pass. This guide walks through how ADU permits actually work here, where the City of San Diego and the County of San Diego differ, and what state law requires of both.

Front view of the completed ADU and remodel at 3545 44th Street, City Heights, San Diego
3545 44th Street, City Heights
Aerial of the rear and new two-story ADU at 4951-57 Genesee Avenue, Clairemont, San Diego
4951 Genesee Avenue, Clairemont
Open kitchen and living area in the 4955 unit at 4951-57 Genesee Avenue, Clairemont, San Diego
ADU interior, 4951 Genesee Avenue, Clairemont

First question: is your lot in the City or the County?

“San Diego” covers several permitting agencies, and the address on your mail doesn’t always tell you which one you answer to.

  • City of San Diego Development Services Department (DSD) handles neighborhoods inside city limits, including Kearny Mesa, Clairemont, North Park, City Heights, Point Loma, Linda Vista, and Mission Hills.
  • County of San Diego Planning & Development Services (PDS) handles unincorporated communities such as Lakeside, Spring Valley, Ramona, Alpine, and Fallbrook.
  • Other incorporated cities like La Mesa, Chula Vista, El Cajon, and Encinitas run their own building departments with their own ADU ordinances.

If you aren’t sure, check your parcel on the County’s assessor or zoning maps before you pay for design work.

What state law guarantees, wherever you build

California ADU law sets the floor for every city and county. A few rules matter most for timing and cost:

  • Ministerial review. An ADU application must be approved or denied without a public hearing or discretionary review (Gov. Code § 66317). If your plans meet the objective standards, there’s no neighbor vote and no planning commission.
  • 15 business days to call it complete. The agency has to tell you in writing whether your application is complete within 15 business days of receiving it.
  • 60 days to decide. On a lot with an existing house, the agency must approve or deny a complete application within 60 days. If it doesn’t act, the application is deemed approved. If you submit the ADU together with a new house, the agency can hold the ADU until it decides on the house.
  • Impact fee relief for smaller units. An ADU with 750 square feet or less of interior livable space is exempt from impact fees charged by local agencies, special districts, and water corporations (Gov. Code § 66311.5). Above 750 square feet, impact fees have to be proportional to the size of the main house. A JADU of 500 square feet or less is also exempt.
  • School fees are separate. School districts may charge fees on ADUs over 500 square feet. Units under 500 square feet are not subject to them.

That 750-square-foot line is worth designing around. A 740-square-foot plan can skip a whole category of fees that a 760-square-foot plan pays.

How the City of San Diego ADU permit works

Inside city limits, an ADU or JADU always needs a Building Permit. The City’s Information Bulletin 400 is direct about it: there are no exemptions. The general ADU regulations live in San Diego Municipal Code Chapter 14, Article 1, Division 3.

What goes in the submittal

Applications are paperless and go through the DSD Application Portal under “Building Construction.” The City’s minimum submittal for an ADU or JADU includes:

  • Site plan and vicinity map (prepared per Information Bulletin 122)
  • Floor plans and roof plans
  • Elevations and sections
  • Structural plans, details, and structural or truss calculations
  • Title 24 energy calculations
  • General Application (DS-3032), Water Meter Data Card (DS-16), and Storm Water Applicability Checklist (DS-560)

The site plan carries more weight than most homeowners expect. It has to show legal lot status, setbacks to property lines and other structures, parking, landscape regulations, and historic resource information. If the existing house is 45 years or older, which describes a lot of Clairemont, North Park, and City Heights, plan on a photographic survey and the County Assessor’s building record as part of the package.

Fees and the order you pay them

DSD reviews the application for completeness and invoices the plan-check fee. Your project goes into the review queue only after that fee is paid. Before the permit is issued you’ll pay inspection and issuance fees, and if your ADU is over 500 square feet you’ll need a receipt or Certificate of Compliance from the school district. Projects over 1,000 square feet also need a construction waste management form.

Corrections come back all at once

Each discipline (structural, energy, planning, and so on) issues its own comments, but you can’t upload corrections until every discipline finishes its cycle, and the responses have to go back as a single consolidated set. One weak sheet holds up the whole project, which is why a clean first submittal matters more than speed to submit.

Preapproved plans

Under AB 1332, the City accepts ADU applications that use preapproved plans and reviews them on a 30-day clock. The City also accepts the County’s permit-ready plans and the City of Encinitas PRADU plans, as long as the package meets City submittal standards. A preapproved plan approves the building design, not your lot. You still need a site plan, utilities, and everything else specific to your property, and you may need to license the plan from its designer.

Coastal Overlay Zone: the step people miss

If your lot is in the City’s Coastal Overlay Zone, which covers parts of Point Loma, Ocean Beach, Pacific Beach, and La Jolla, an ADU usually needs a Coastal Development Permit (CDP) on top of the building permit. Per IB 400, a CDP is required for any ADU or JADU that isn’t fully inside the existing house, adds habitable area, or converts non-habitable space such as a garage.

The good news: since September 7, 2022, ADUs in the non-appealable part of the coastal zone can get a City-issued CDP processed with the building permit (Process One) when the administrative findings are met, and the City’s CDP decision on an ADU can’t be appealed to the California Coastal Commission. A JADU fully inside the existing house may qualify for a coastal exemption.

How the County of San Diego ADU permit works

In unincorporated communities, PDS handles ADUs and JADUs on residential lots that already have, or will have, a main house. A few things are different from the City:

  • The fee waiver is over. The County’s trial ADU fee waiver ran from January 9, 2019 to January 9, 2024. New projects pay the County’s standard plan-review and permit fees, and the Building Division invoices plan-check fees at submittal.
  • Preapproved plans have been around since 2019. The County’s plans are a head start, not a finished permit set. You still complete project-specific sheets and a site plan for your lot.
  • Green Building discount. Under the County’s Green Building Program, projects that meet one of its sustainability tracks (for example, beating the state energy standards by 15% for residential) get plan check and permit fees reduced by 7.5%.
  • Site conditions drive cost. Rural lots often bring septic capacity questions, slopes, and longer utility runs that a city lot in Kearny Mesa never sees.
  • Separate sale is now possible. The County adopted AB 1033 rules effective April 4, 2026, allowing ADUs in unincorporated areas to be sold separately through a condominium process. That takes a separate map application.

Title 24 and solar on a new ADU

Every ADU submittal in either jurisdiction needs Title 24 energy calculations. Under the California Energy Code, a newly constructed detached ADU generally needs a solar PV system, while attached units and conversions are evaluated differently. Your energy consultant’s report decides the system size, the insulation, the windows, and the HVAC and water heater specs so do it before structural engineering is final.

How we approach ADU permits at Ballow Construction

We’ve been building in San Diego since 1991 (CA License #636290), and we run our own development projects, so we look at an ADU the way an owner does: what will it cost, how long until it’s rented or lived in, and what adds value. On permits, that means confirming jurisdiction, coastal status, and utility capacity before drawings start, sizing the unit with the 500- and 750-square-foot fee lines in mind, and coordinating the designer, structural engineer, and Title 24 consultant so the first submittal is complete.

You can see ADU work we’ve completed in the City of San Diego, including 3545 44th Street and 4951 Genesee Ave, on our Past Performance page. For the full picture of ADU types and how we build them, start with our San Diego ADU builder page or the rest of our construction services.

ADU permit FAQ

Do I need a permit to build an ADU in San Diego?

Yes. The City of San Diego requires a Building Permit for every ADU and JADU with no exemptions, and the County requires one in unincorporated areas too. Garage conversions and JADUs inside the house need permits as well.

How long does the City of San Diego take to approve an ADU?

State law gives the City 15 business days to confirm your application is complete and 60 days to approve or deny a complete application on a lot with an existing home. Preapproved plans get a 30-day review. Correction cycles add time, so a complete first submittal is the biggest factor you control.

Are ADU impact fees waived in San Diego?

Impact fees are waived for ADUs of 750 square feet or less of interior livable space under state law, in both the City and the County. Larger units pay proportional impact fees. School district fees can still apply to ADUs over 500 square feet, and plan-check and permit fees apply to every ADU.

Do I need a Coastal Development Permit for an ADU?

Usually, if the lot is in the City’s Coastal Overlay Zone and the ADU adds habitable area, sits outside the existing house, or converts non-habitable space. In the non-appealable coastal area, the City can issue that CDP with the building permit when its administrative findings are met.

Can I use the County’s preapproved ADU plans in the City of San Diego?

Yes. The City accepts the County’s permit-ready ADU plans and the City of Encinitas PRADU plans, as long as the package meets City Building Permit submittal requirements, including a site plan for your lot.

Does a new ADU need solar panels?

A newly constructed detached ADU generally needs solar PV under the California Energy Code. Attached ADUs, JADUs, and conversions are treated differently. Your Title 24 energy report confirms what your specific design requires.

Talk to us before you draw

If you’re weighing an ADU in San Diego, a short conversation before design can save months of corrections. Call us at 858-384-6243 or send us your address and project details, and we’ll tell you which agency you’re dealing with and what your lot needs.